The process of building the cabin, in chronological order.
Post 11 Debarking

Tuesday, 10 August 2021
The debarking of our felled trees took far longer than we thought as it is a very labour intensive and slow process.
Read morePost 12 Treating the logs

Friday, 13 August 2021
A very common question that we are asked all the time is how we treated the logs against bugs and borer.
Read morePost 13 The build - rigging and cranes

Wednesday, 29 December 2021
After a long winter break, attending to commitments in our respective work places at home, Simon and I resumed our log cabin build.
Read morePost 14 The build - Selection of logs and first layer

Wednesday, 5 January 2022
It was with much anticipation that we selected the first 4 logs for the first layer. These needed to be our best logs as the entire log cabin was going to rest on that layer.
Read morePost 15 The build - fastening and securing logs together

Wednesday, 5 January 2022
Fastening the logs together is of course crucial and a key aspect of building with logs.
Read morePost 16 The build - hoisting logs with chain blocks

Wednesday, 5 January 2022
One of the first questions that many onlookers ask is how do we hoist the logs so high.
Read morePost 17 The build - layer by layer

Thursday, 17 February 2022
After laying the first few layers we could calculate that it would take about 12 layers of logs to reach ceiling height.
Read morePost 18 The build – mezzanine height and vertical uprights

Friday, 18 February 2022
As the build progressed we could calculate that we needed to position about 11 layers of logs to reach ceiling/mezzanine height.
Read morePost 19 The build – final layer

Wednesday, 20 April 2022
After three months of stacking layer upon layer, we finally reached our last one, the 15th layer.
Read more